SAFe SPC Sample Exam (50 difficult questions)

…/…
Question 1

Deliver early and often is part of which lean-agile principle?

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
#2 Apply systems thinking 0
Should not have chosen
#1 Take an economic view 0
Should have chosen
#3 Assume variability, preserve options 0
Should not have chosen
#7 Apply Cadence and synchronise with cross domain planning 0
Should not have chosen
#6 Visualise and limit WIP, reduce batch sizes and manage queue lengths 0
Should not have chosen
Selected
#4 Build incrementally with fast, integrated learning cycles
Incorrect
0
Should not have chosen
#9 Decentralise Decision Making 0
Should not have chosen
#8 Unlock the intrinsic motivation of knowledge workers 0
Should not have chosen
#5 base milestones on objective valuation of working systems 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the link below

http://www.scaledagileframework.com/safe-lean-agile-principles/

Question 2

Provide Time and Spce for Creativity is part of which pillar of the House of Lean?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Quality 0
Should not have chosen
Selected
Respect for people and culture
Incorrect
0
Should not have chosen
Flow 0
Should not have chosen
Leadership 0
Should not have chosen
Relentless Improvement 0
Should not have chosen
Innovation 0
Should have chosen

The concepts are part of the House of Lean pillar of INNOVATION

http://www.scaledagileframework.com/lean-agile-mindset/

Pillar 3 – Innovation

Question 3

Select the elements of an agile team in SAFe

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
self-managing 0
Should have chosen
Delivers valuable tested software every 2 to 4 weeks. 0
Should not have chosen
Selected
uses the best of scrum, XP and Kanban
Correct
1
Should have chosen
Selected
Self-organising
Correct
1
Should have chosen
Selected
Empowered
Correct
1
Should have chosen

in general agile teams can deleiver anywhere between 1-4 weeks and 2 weeks is common.

But for SAFe the period is fixed at 2 weeks because, in SAFe, multiple agile teams must coordinate and align together, so it is important to have the same cadence.

 

This page has more information http://www.scaledagileframework.com/scrumxp/

Question 4

In SAFe(r) which of the following is not a feature of setting a vision for change

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Faster Deployment
Correct
1
Should have chosen
Improved Motivation 0
Should not have chosen
Clarified Purpose 0
Should not have chosen
Better Alignment 0
Should not have chosen

Establishing the vision for change is part of reaching the tipping point.

For more information see:

http://www.scaledagileframework.com/reaching-the-tipping-point/

http://www.scaledagileframework.com/

Question 5

We have identified the ARTs

What is the next step in the process?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Identify the systems that support the operational values streams 0
Should not have chosen
If necessary, split ARTs in large value streams into multiple ARTs 0
Should have chosen
Identify Development Streams Cross Boundaries effects 0
Should not have chosen
Selected
Identify the people that develop the systems
Incorrect
0 This is the recommended scrum team size
Should not have chosen
Define the Development Value Streams 0
Should not have chosen
Identify the ARTs 0
Should not have chosen
Identify the operational value streams 0
Should not have chosen

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/

Question 6

What uses the concept of Minimum Viable Product and quantifiable metrics focused on outcomes to support company strategy

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Business owners 0
Should not have chosen
MUDA 0
Should not have chosen
Lean Governance 0
Should not have chosen
Innovation Accounting 0
Should have chosen
GEMBA 0
Should not have chosen
MBWA 0
Should not have chosen
Selected
Lean Product Development
Incorrect
0
Should not have chosen
Agile-Scrum 0
Should not have chosen

Innovation Accounting (Eric Ries) uses the following three basic steps:

1)  It uses a minimal viable product (MVP) to establish real data on where the company stands at any
given juncture.  An MVP is the fastest way to establish a customer feedback loop with minimal output of effort.

Its primary goal is to test fundamental business hypotheses without having to perfect the product or service in question too prematurely.

2)  Using the MVP, start-ups, through many attempts, move from the baseline to the ideal, when the company then reaches a decision point.

3)  At this juncture, a company is either making solid progress toward the ideal enough that it makes sense to continue, or persevere.  If not, the strategy must be deemed flawed and in need of serious change―or as Ries labels it, a pivot, which starts the process all over again and in a more productive fashion than before.

 

Links:

http://lexicon.ft.com/Term?term=innovation-accounting

http://theleanstartup.com/

https://www.businessopportunity.com/Blog/innovation-accounting-lean-star…

 

 

Question 7

One of the strengths of SAFe(r) is its ability to be flexed without limit to fit any particular company environment.

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
True 0
Should not have chosen
False 0
Should have chosen

SAFe(r) is a framework which is based on globally referable practices. It can be flexed within limits, but dilution of any key areas will lead to loss of benefit.

For more information see:

http://www.scaledagileframework.com/implementation-roadmap/

http://www.scaledagileframework.com/

Question 8

What SAFE® principle allows people to do the following:

  • Communicate across functional boundaries.
  • Make decisions based on an understanding of the economics.
  • Receive fast feedback about the efficacy of their solution.
  • Participate in continuous, incremental learning and mastery.
  • Participate in a more productive and fulfilling solution development process.

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
#3 – Assume variability; preserve options 0
Should not have chosen
#1 – Take an economic view 0
Should not have chosen
#9 – Decentralize decision-making 0
Should not have chosen
#8 – Unlock the intrinsic motivation of knowledge workers 0
Should have chosen
#6 – Visualize and limit WIP, reduce batch sizes, and manage queue lengths 0
Should not have chosen
#4 – Build incrementally with fast, integrated learning cycles 0
Should not have chosen
#5 – Base milestones on objective evaluation of working systems 0
Should not have chosen
#2 – Apply systems thinking 0
Should not have chosen
#7 – Apply cadence, synchronize with cross-domain planning 0
Should not have chosen

This is part of principle 8 – Unlock the intrinsic motivation of knowledge workers

For more information read:

http://www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/

Question 9

Which of the following statements is not true about optimum batch size?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Higher transaction costs shift optimum batch size higher 0
Should not have chosen
The optimal batch size is calaculated by identifying the total cost (holding plus transaction) acorss a range of batch sizes and selecting the lowest total cost 0
Should not have chosen
Optimal batch size is a tradeoff between holding cost and transaction cost 0
Should not have chosen
Higher holding costs shift optimal batch sizes lower

 

0
Should not have chosen
The total cost is always highest at the point where the transaction cost curve and the holding cost curve intersect 0
Should have chosen

This is part of principle #6 – Visualize and limit WIP, reduce batch sizes, and manage queue lengths

For more information read:

https://zsoltfabok.com/blog/2013/03/the-optimal-batch-size/

http://www.scaledagileframework.com/visualize-and-limit-wip-reduce-batch-sizes-and-manage-queue-lengths/

Question 10

Emphasize life-long learning, is part of which element of the House of Lean?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Relentless Improvement
Incorrect
0
Should not have chosen
Quality 0
Should not have chosen
Flow 0
Should not have chosen
Governance 0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Value 0
Should not have chosen
Innovation 0
Should not have chosen
Leadership 0
Should have chosen

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/

Foundation – Leadership

Question 11

The notion that flexible requirements and design allows economic tradeoffs to be made is part of which lean-agile principle?

 

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
#1 Take an economic view 0
Should not have chosen
#8 Unlock the intrinsic motivation of knowledge workers 0
Should not have chosen
#6 Visualise and limit WIP, reduce batch sizes and manage queue lengths 0
Should not have chosen
#5 base milestones on objective valuation of working systems 0
Should not have chosen
#7 Apply Cadence and synchronise with cross domain planning 0
Should not have chosen
#2 Apply systems thinking 0
Should not have chosen
Selected
#3 Assume variability, preserve options
Correct
1
Should have chosen
#4 Build incrementally with fast, integrated learning cycles 0
Should not have chosen
#9 Decentralise Decision Making 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the links below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

http://www.scaledagileframework.com/assume-variability-preserve-options/

 

Did you select Economic Thinking?  The two are related. Flexible Design and requirements are part of Principle 3.  The thinking to even do economic tradeoffs is part of principle 1.

Question 12

Lead the change, is part of which element of the House of Lean?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Governance 0
Should not have chosen
Selected
Leadership
Correct
1
Should have chosen
Value 0
Should not have chosen
Quality 0
Should not have chosen
Flow 0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Innovation 0
Should not have chosen
Relentless Improvement 0
Should not have chosen

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/

Foundation – Leadership

Question 13

Reflect at key milestones then identify and address shortcomings, is part of which pillar of the House of Lean?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Innovation 0
Should not have chosen
Quality 0
Should not have chosen
Selected
Relentless Improvement
Correct
1
Should have chosen
Flow 0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Leadership 0
Should not have chosen

The concepts are part of the House of Lean pillar of Relentless Improvement

http://www.scaledagileframework.com/lean-agile-mindset/

Pillar 4 – Relentless Improvement

Question 14

Build Quality in is part of which pillar of the House of Lean?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Respect for people and culture 0
Should not have chosen
Leadership 0
Should not have chosen
Quality 0
Should not have chosen
Relentless Improvement 0
Should not have chosen
Selected
Value
Incorrect
0
Should not have chosen
Flow 0
Should have chosen

The concepts are part of the House of Lean pillar of FLOW (Build Quality in; Flow depends on it)

http://www.scaledagileframework.com/lean-agile-mindset/

Pillar 2 – Flow

Question 15

Increased predictability, accelerated feedback, reduction in rework, lower risk, and lower cost are all direct benefits of …

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
reducing batch size
Correct
1
Should have chosen
Program Increment (PI) Planning 0
Should not have chosen
shortening iteration length 0
Should not have chosen
system demos 0
Should not have chosen

This is part of principle #6 – Visualize and limit WIP, reduce batch sizes, and manage queue lengths

For more information read:

https://zsoltfabok.com/blog/2013/03/the-optimal-batch-size/

http://www.scaledagileframework.com/visualize-and-limit-wip-reduce-batch-sizes-and-manage-queue-lengths/

Question 16

 

Fill in the blanks

The principle of  ______ tells us that :

  • Most problems with our process will surface as ______
  • Most of the time spent getting to market is as a result of _______
  • Reducing _____ is the fastest way to reduce time to market

 

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Build incrementally with fast integrated learning cycles; Defects; Delays; Defects 0
Should not have chosen
Selected
Systems Thinking; Defects; Delays; Delays
Incorrect
0
Should not have chosen
Systems Thinking; Delays; Delays; Delays 0
Should have chosen
Build incrementally with fast integrated learning cycles; Delays; Delays; Delays 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the links below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

http://www.scaledagileframework.com/apply-systems-thinking/

Question 17

What is the IP iteration

 

 

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Intellectual Property iteration 0
Should not have chosen
Selected
Innovation and Planning iteration
Correct
1
Should have chosen
Internal Process iteration 0
Should not have chosen

Read more at: http://www.scaledagileframework.com/guidance-six-safe-practices-for-s-sized-teams/

 

Question 18

In SAFe(r) – which of the below is NOT one of the four critical moves designed to create a sense of urgency and establish a powerful coalition

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Train Executives, Managers, and Leaders 0
Should not have chosen
Identify Value Streams and ARTs 0
Should have chosen
Create a Lean-Agile Centre of Excellence 0
Should not have chosen
Train Lean-Agile Change Agents 0
Should not have chosen
Selected
Reaching the Tipping Point
Incorrect
0 This is the recommended scrum team size
Should not have chosen

Identify Value Streams and ARTs comes after creating the conditions for change, and is the first step in implementing change.

the four key moves are:

  1. Reaching the Tipping Point
  2. Train Lean-Agile Change Agents
  3. Train Executives, Managers, and Leaders
  4. Create a Lean-Agile Centre of Excellence (LACE)

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/ and http://www.scaledagileframework.com/implementation-roadmap/

 

Question 19

Pivot without Mercy or Guilt is part of which pillar of the House of Lean?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Respect for people and culture 0
Should not have chosen
Leadership 0
Should not have chosen
Flow 0
Should not have chosen
Selected
Innovation
Correct
1
Should have chosen
Relentless Improvement 0
Should not have chosen
Quality 0
Should not have chosen

The concepts are part of the House of Lean pillar of INNOVATION

http://www.scaledagileframework.com/lean-agile-mindset/

Pillar 3 – Innovation

Question 20

What is the minimum size of an agile release train (ART)?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
the dunbar number 0
Should not have chosen
a minimum of one scrum team 0
Should not have chosen
Selected
Around 50 people
Correct
1
Should have chosen
50-125 people 0
Should not have chosen

An ART is a group of 50-125 people that plan, commit and execute together on the program increment.

The minimum size of the ART is therefore around 50 people.  Below that the economies of scale are not present enough to justify SAFe(r) adoption

For more information:

http://www.scaledagileframework.com/agile-release-train/

Question 21

How is value defined in Lean-Agile?

 

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Deliver the maximum customer value in the shortest sustainable lead time, while providing the highest possible quality to Customers and society as a whole
Correct
1
Should have chosen
Understand current and future customer needs, meet customer requirements and strive to exceed customer expectations 0
Should not have chosen
Consider the needs of all interested parties including customers, owners, employees, suppliers, financiers, local communities and society as a whole 0
Should not have chosen
Create and maintain the internal environment in which people can become fully involved in achieving the organization’s objectives 0
Should not have chosen
Identify, understand and manage interrelated processes in the system to contribute to the organization’s effectiveness and efficiency in achieving its objective 0
Should not have chosen

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/

The Goal – Value

Question 22

We have identified the people that develop the systems

What is the next step in the process?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Identify the systems that support the operational values streams 0
Should not have chosen
Identify the people that develop the systems 0
Should not have chosen
If necessary, split ARTs in large value streams into multiple ARTs 0
Should not have chosen
Selected
Identify the operational value streams
Incorrect
0
Should not have chosen
Identify the ARTs 0
Should not have chosen
Identify Development Streams Cross Boundaries effects 0
Should not have chosen
Define the Development Value Streams 0
Should have chosen

 

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/

Question 23

What is the primary reason that requires the establishment of some form of LACE in SAFe(r)

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Because we need to take an agile, incremental, approach to implementation, just as we do with solution development 0
Should not have chosen
Selected
The people qualified to drive the change usually have full-time responsibilities in their current roles; While they can support change with a portion of their time, a smaller, more dedicated group of people is required to drive the transformation throughout the organization.  The primary task of these latter group of people is to drive and implement change.
Correct
1
Should have chosen
because we need to « Train everyone; Launch the Train » 0
Should not have chosen
People naturally resist change and for this reason the organisation must reach the point where the compelling imperative is to achieve the change rather than resist it 0
Should not have chosen

The other answers are all valid concepts but do not relate to the question.

Read more at: http://www.scaledagileframework.com/LACE/

Question 24

In SAFe(r) what two things can independently cause organisations to reach a tipping point

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Proactive leadership and vendor partners 0
Should not have chosen
Burning platform and proactive leadership 0
Should have chosen
Vendor partners and organic change 0
Should not have chosen
Industry trends and vendor partners 0
Should not have chosen
Selected
Organic change and burning platform
Incorrect
0
Should not have chosen

For more information see:

http://www.scaledagileframework.com/reaching-the-tipping-point/

http://www.scaledagileframework.com/

Question 25

Peter Drucker says that « to effectively lead, workers must be heard and respected ».

What principle applies to this?

 

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
#3 – Assume variability; preserve options 0
Should not have chosen
#2 – Apply systems thinking 0
Should not have chosen
#5 – Base milestones on objective evaluation of working systems 0
Should not have chosen
#6 – Visualize and limit WIP, reduce batch sizes, and manage queue lengths 0
Should not have chosen
#9 – Decentralize decision-making 0
Should not have chosen
Selected
#4 – Build incrementally with fast, integrated learning cycles
Incorrect
0
Should not have chosen
#8 – Unlock the intrinsic motivation of knowledge workers 0
Should have chosen
#1 – Take an economic view 0
Should not have chosen
#7 – Apply cadence, synchronize with cross-domain planning 0
Should not have chosen

This is part of principle 8 – Unlock the intrinsic motivation of knowledge workers

– Create an Environment of Mutual Influence

For more information read:

http://www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/

Question 26

Complete the following phrase

‘A system can evolve no faster than… »

 

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
the lead time of the system 0
Should not have chosen
the ability of management to absorb 0
Should not have chosen
the velocity of the adoption of change 0
Should not have chosen
Selected
its slowest intergation point
Correct
1
Should have chosen
the cycle time of the system 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

Question 27

Understanding, exploiting and managing variability, and frequent integrations are part of :

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Relentless improvement

 

0
Should not have chosen
Leadership 0
Should not have chosen
Selected
Flow
Correct
1
Should have chosen
Value 0
Should not have chosen
Innovation 0
Should not have chosen
Agile-scrum 0
Should not have chosen
Quality 0
Should not have chosen

The concepts are part of the House of Lean pillar of FLOW

http://www.scaledagileframework.com/lean-agile-mindset/

Pillar 2 – Flow

 

 

Question 28

Which of the following is not a ‘critical program role’ in SAFe(r)

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Business Owner 0
Should not have chosen
System Architect/Engineer 0
Should not have chosen
Selected
Product Owner
Correct
1
Should have chosen
Release Train Engineer 0
Should not have chosen

The product owner is a TEAM role (Scrum team) not a program level role.

For more information:

http://www.scaledagileframework.com/agile-release-train/

Question 29

In SAFe(r) – what group is responsible for the following?

  • Communicating the business need, urgency, and vision for change
  • Developing the implementation plan and managing the transformation backlog
  • Establishing the metrics
  • Conducting or sourcing training for executives, managers and leaders, development teams, and specialty roles
  • Identifying Value Streams and helping define and launch Agile Release Trains (ARTs)
  • Providing coaching and training to ART stakeholders and teams
  • Participating in critical, initial events like Program Increment (PI) Planning and Inspect and Adapt (I&A)
  • Fostering SAFe Communities of Practice (CoPs)
  • Communicating progress Implementing Lean-Agile focus days, with guest speakers, and presenting internal case studies
  • Benchmarking and connecting with the external community
  • Promoting continuing Lean-Agile education
  • Extending Lean-Agile practices to other areas of the company, including Lean Budgets, Lean Portfolio Management, contracts, and human resources
  • Helping to establish relentless improvement
Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
The Portfolio Team 0
Should not have chosen
Selected
The LACE
Correct
1
Should have chosen
The Program Team 0
Should not have chosen

This vast list of responsibilities are all assigned to the Lean Agile Centre of Excellence (LACE)

Read more at: http://www.scaledagileframework.com/LACE/

 

Question 30

The four pillars of the House of Lean are:

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Respect for people and culture, Quality, Innovation, Relentless improvement 0
Should not have chosen
Respect for people and culture, Flow, Leadership, Relentless improvement 0
Should not have chosen
Selected
Respect for people and culture, Flow, Innovation, Relentless improvement
Correct
1 Correct these are the pillars, leadership forms the base and Value forms the roof.
Should have chosen
Respect for people and culture, Leadership, Value, Relentless improvement 0
Should not have chosen
Respect for people and culture, Value, Innovation, Relentless improvement 0
Should not have chosen
Question 31

We have identified Development Streams Cross Boundaries effects

What is the next step in the process?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Define the Development Value Streams 0
Should not have chosen
Selected
Identify the systems that support the operational values streams
Incorrect
0
Should not have chosen
Identify Development Streams Cross Boundaries effects 0
Should not have chosen
Identify the operational value streams 0
Should not have chosen
Identify the people that develop the systems 0
Should not have chosen
Identify the ARTs 0
Should have chosen
If necessary, split ARTs in large value streams into multiple ARTs 0
Should not have chosen

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/

Question 32

What is the benefit of successive iterations with objective milestones?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
It allows for phase-gates at iteration points 0
Should not have chosen
Selected
It provides inspection and adaption opportunities allowing for continuous adjustments of the solution towards an optimal result
Correct
1
Should have chosen
It allows governance to determine risk profiles at specific intervals

 

0
Should not have chosen
It provides for gates where the project can be assessed against criteria for persist, pivot or perish (The three Ps) 0
Should not have chosen

This is part of principle #5base milestones on objective evaluation of working systems.

See:

http://www.scaledagileframework.com/base-milestones-on-objective-evaluation-of-working-systems/

 

Question 33

Select the item that is not an aspect of systems thinking

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
The solution itself is a system 0
Should not have chosen
Selected
Optimise the full value stream
Incorrect
0
Should not have chosen
Synchronise with cross domain planning 0
Should have chosen
The organisation building the solution is a system 0
Should not have chosen
Optmising a component does not optimise a system 0
Should not have chosen
The value of a system passes through its interconnections 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the link below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

 

Apply cadence and synchronise with cross domain planning is a principle in its own right (#7)

Question 34

In SAFe(r) – What is the purpose of an operational value stream?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
It is used to build systems and capabilities that enable operational value streams. 0
Should not have chosen
It is used to identify the steps, value, people and systems and lead time. 0
Should not have chosen
Selected
It is used to deliver customer end value.
Correct
1 This is the recommended scrum team size
Should have chosen

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/

Question 35

Select the item in the list below that is NOT part of forming the ‘sufficiently powerful guiding coalition’ in SAFe(r)

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Train everyone; Launch the Train 0
Should have chosen
Selected
Charter a LACE
Incorrect
0
Should not have chosen
Train executives, managers, and other leaders 0
Should not have chosen
Train a number of Lean-Agile change agents as SAFe Program Consultants (SPCs) 0
Should not have chosen

« Train Everyone; Launch the train » is not part of forming the guiding coalition, it is part of the implementation roadmap.

 

Read more at: http://www.scaledagileframework.com/LACE/

Question 36

What does LACE mean?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Lean Agile Centre of Excellence
Correct
1
Should have chosen
Look; Assess; Change; Extend 0
Should not have chosen
Low Automation; Clear Expression 0
Should not have chosen

Read more at: http://www.scaledagileframework.com/LACE/

Question 37

Face to face planning for collaboration, alignment and adaption is desirable if possible but not essential for geographically remote agile teams on the same ART, which are endorsed to carry out their own planning activitioes, suited to their time zone and particular needs, especially in cases where different languages are in use.

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
True
Incorrect
0
False 0
Should have chosen

Face-to-face planning is a key agile and SAFe concept that is always recommended to be followed. Only in circumstances where it is simply too costly or too infeasible is this rule able to be avoided, and in such a case the focus ought to be on splitting up the work to allow it to be co-located.

 

Question 38

The notion that improvement comes through synchronisation of design loops and shorter learning cycles is part of which lean-agile principle?

 

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
#7 Apply Cadence and synchronise with cross domain planning 0
Should not have chosen
#3 Assume variability, preserve options 0
Should not have chosen
#6 Visualise and limit WIP, reduce batch sizes and manage queue lengths 0
Should not have chosen
#9 Decentralise Decision Making 0
Should not have chosen
#1 Take an economic view 0
Should not have chosen
Selected
#4 Build incrementally with fast, integrated learning cycles
Correct
1
Should have chosen
#5 base milestones on objective valuation of working systems 0
Should not have chosen
#8 Unlock the intrinsic motivation of knowledge workers 0
Should not have chosen
#2 Apply systems thinking 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the links below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

http://www.scaledagileframework.com/build-incrementally-with-fast-integrated-learning-cycles/

Question 39

One of the following is not a principle of the House of lean, which is it?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Velocity
Correct
1
Should have chosen
Leadership 0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Relentless improvement 0
Should not have chosen
Innovation 0
Should not have chosen
Value 0
Should not have chosen
Flow 0
Should not have chosen

The lean agile mindset is represented by the house of lean: http://www.scaledagileframework.com/lean-agile-mindset/

 

Question 40

Reducing costs by dropping unsuccessful paths quickly is part of which lean-agile principle?

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
#8 Unlock the intrinsic motivation of knowledge workers 0
Should not have chosen
#5 base milestones on objective valuation of working systems 0
Should not have chosen
Selected
#1 Take an economic view
Incorrect
0
Should not have chosen
#2 Apply systems thinking 0
Should not have chosen
#3 Assume variability, preserve options 0
Should not have chosen
#7 Apply Cadence and synchronise with cross domain planning 0
Should not have chosen
#6 Visualise and limit WIP, reduce batch sizes and manage queue lengths 0
Should not have chosen
#4 Build incrementally with fast, integrated learning cycles 0
Should have chosen
#9 Decentralise Decision Making 0
Should not have chosen

For more information on SAFe Lean-Agile principles go to the links below:

http://www.scaledagileframework.com/safe-lean-agile-principles/

http://www.scaledagileframework.com/build-incrementally-with-fast-integrated-learning-cycles/

Question 41

Why must autonomy for the team be unconstrained?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Because, otherwise, natural leaders may emerge 0
Should not have chosen
Selected
It is a myth that autonomy be unconstrained, the needs of purpose of the organisation always constrain autonomy
Correct
1
Should have chosen
Because the intrinsic innovation and creativity of teams is only unlocked when free of all constraint 0
Should not have chosen
Because if not, then teams will ultimately fall back into old patterns of command and control 0
Should not have chosen

it is indeed a myth that autonomy (and self-organisation) of teams be unconstrained.  Such an approach, especially in a scaled environment, would lead to chaos.

Yet it is also true that innovation and creativity come from teams operating with the optimal level of self-organisation and autonomy, within the framework of the organisation.

When Demingh says that management cannot delegate change, this is part of what cannot be delegated.

Autonomy and self-organisation must have clear boundaries, aligned to organisational purpose.

This is part of principle 8 – Unlock the intrinsic motivation of knowledge workers

For more information read:

http://www.scaledagileframework.com/unlock-the-intrinsic-motivation-of-knowledge-workers/

Question 42

Complete the quote from Don Reinertsen:

The more detailed we made our plans,….

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
the less variability we had in implementation 0
Should not have chosen
the more accurate our estimations 0
Should not have chosen
the more effective we became 0
Should not have chosen
Selected
the longer our cycle times became
Correct
1
Should have chosen

Read more at: http://www.scaledagileframework.com/create-the-implementation-plan/

Question 43

Select the correct answer from the following

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
An Agile Release Train in Essential SAFe is called  a Solution Train in Large Solution SAFe 0
Should not have chosen
Selected
On Solution Train can contain one or more Agile Release Trains
Correct
1
Should have chosen
On Agile Release Train can contain one or more  Solution Trains 0
Should not have chosen

Large Solution SAFe coordinates multiple Agile Release Trains with a Solution Train

Question 44

Informed decision making via fast feedback is part of what?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Flow
Correct
1
Should have chosen
Leadership 0
Should not have chosen
Value 0
Should not have chosen
Relentless Improvement 0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Quality 0
Should not have chosen

The concepts are part of the House of Lean pillar of FLOW

http://www.scaledagileframework.com/lean-agile-mindset/

Pillar 2 – Flow

Question 45

Fill in the blanks

_______ is the rhythmic heartbeat of the process; it makes ________ that which can be ________

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Cadence |  routine | made routine

 

0
Should have chosen
Program Increment (PI) Planning  | defined, agreed and visible | identified for the next PI 0
Should not have chosen
Synchronised wait time | regular | standardized 0
Should not have chosen
Selected
Timeboxing |  standard  | defined and agreed
Incorrect
-1
Should not have chosen

This is part of principle #7 – Apply cadence, synchronize with cross-domain planning

 

For more information read:

http://www.scaledagileframework.com/apply-cadence-synchronize-with-cross-domain-planning/

Question 46

What are the 4 core values of SAFe?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Selected
Built-in Quality
Incorrect
-1
Should not have chosen
Selected
Alignment
Incorrect
-1
Should not have chosen
Selected
Transparency
Incorrect
-1
Should not have chosen
Empowerment 0
Should not have chosen
Value Realisation 0
Should not have chosen
Selected
Program execution
Incorrect
-1
Should not have chosen

Built in quality, program Execution, Alignment, and Transparency – see this site page : http://www.scaledagileframework.com/safe-core-values/

Try using mnemonics to remember things like this, for example the upper case letters in the list above spell the word BEAT.

if you think of core values as the ‘heartBEAT’ of SAFe then remembering the mnemonic is easier

Question 47

Develop People, is part of which element of the House of Lean?

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Leadership 0
Should have chosen
Governance 0
Should not have chosen
Selected
Relentless Improvement
Incorrect
0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Quality 0
Should not have chosen
Innovation 0
Should not have chosen
Flow 0
Should not have chosen
Value 0
Should not have chosen

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/

Foundation – Leadership

Question 48

We have defined the Development Value Streams

What is the next step in the process?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Identify the operational value streams 0
Should not have chosen
If necessary, split ARTs in large value streams into multiple ARTs 0
Should not have chosen
Identify the ARTs 0
Should not have chosen
Define the Development Value Streams 0
Should not have chosen
Selected
Identify Development Streams Cross Boundaries effects
Correct
1
Should have chosen
Identify the systems that support the operational values streams 0
Should not have chosen
Identify the people that develop the systems 0
Should not have chosen

Read more at: http://www.scaledagileframework.com/identify-value-streams-and-arts/

Question 49

Align with Mission and remove constraints, is part of which element of the House of Lean?

Score: 1 of 1
Your answer Choice Correct? Score Feedback Correct answer
Relentless Improvement 0
Should not have chosen
Quality 0
Should not have chosen
Respect for people and culture 0
Should not have chosen
Flow 0
Should not have chosen
Governance 0
Should not have chosen
Value 0
Should not have chosen
Innovation 0
Should not have chosen
Selected
Leadership
Correct
1
Should have chosen

The concepts are part of the House of Lean foundation of Leadership

http://www.scaledagileframework.com/lean-agile-mindset/

Foundation – Leadership

Question 50

Which of the following is NOT a leadership style identified by Bradford and Cohen?

 

 

Score: 0 of 1
Your answer Choice Correct? Score Feedback Correct answer
Developer 0
Should not have chosen
Selected
Expert
Incorrect
0
Should not have chosen
Conductor 0
Should not have chosen
Inspirer 0
Should have chosen

The three leadership types are:

  • Leader as expert
  • Leader as conductor
  • Leader as developer

SAFe favours theLeader as developer approach

Read more at: http://www.scaledagileframework.com/lean-agile-leaders/