Test certification Scrum n°1 (1) : 24 questions

octobre 23, 2015

Scrum test (24 questions)

1- If you are truly doing scrum, you should release to production at the end of each sprint.

A-True

B-False


2- What is the most effective way to order the product backlog ?

A-it is up to the Product Owner to decide.

B-Risk

C-Complexity

D-Size


3- Time can be allocated between sprints for integration testing.

A-True

B-False


4- In scrum teams decide which events take place during a sprint.

A-True

B-False


5- Which two things do not occur in the first sprint ?

A-Develop the complete architecture.

B-Finalize the complete product backlog

C-Develop something of value to the customer.

D-Create potentially release software.


6- Who is responsible for maximizing the value of the product backlog ?

A-Customer

B-Product owner

C-Product owner and team

D-Scrum Master and product owner


7- What type of process in scrum ?

A-Empirical

B-Classical

C-Inspection

D-Adaptative


8- In what ways do the product owner manage the value of the product ?

(pick two)

A- User acceptance testing

B- Product Backlog order

C- MoSCoW analysis

D- Customer feedback via frequent releases


9- What are two ways in which the Product Owner manage Inspection of the increment ?

A- By presenting the status of the Product Backlog at the Sprint Review

B- By reviewing it during Product Backlog Refinement

C- By inviting stakeholders to give feedbacks during the Sprint Review

D- By attending the Sprint Retrospective


10- Work that does not meet the definition of Done should be completed in the next Sprint.

A- False

B- True


11- Which of the following terms are optional in Scrum ? (pick two)

A- Burdown

B- Definition of Done

C- Backlog

D- Increment

E- Velocity


12- When is a sprint finished ?

A- When the time-boxed duration is met

B- When the Product Owner accepts the Increment

C- When the definition of Done is met

D- When the work remaining is zero


13- Who tracks work remaining in the Product Bcklog ?

A- Scrum Master

B- Development Team

C- Product Owner

D- Senior executives


14- What scrum event or artifact is the single source of requirements for any change to be made for the product ?

A- Daily Scrum

B- Increment

C- Product Backlog

D- Scrum

E- Sprint


15- The Product Owner must frequently review Scrum artifacts and progress toward a Sprint Goal to detect indesirables variances. Which pillar of Scrum does this represent ?

A- Transparency

B- Inspection

C- Adaptation


16- What is the standard time for the Daily Scrum?

  1. 5 minutes
  2. 15 minutes
  3. 30 minutes
  4. As long as it takes

 

17- The company director approaches a member of the development team to add some new functionality in to the current Sprint. What should they do?

  1. Add it in to the Sprint
  2. Add it in to the Sprint and remove a similar sized piece of work
  3. Add it in to the next Sprint
  4. Inform the Product Owner and get the two talking asap

 

18- Scrum is the appropriate weapon of choice for any kind of software development?

  1. true
  2. false

19- How should the Product backlog be organised?

  1. Longer tasks at the top
  2. Easier tasks at the top
  3. Most important at the top
  4. Randomly

20- Which of the following is NOT an artifact in a typical Scrum project?

  1. Product backlog
  2. Gantt chart
  3. Sprint backlog
  4. Burndown char

21- Which of the following is NOT a Scrum role?

  1. Project manager
  2. Team
  3. ScrumMaster
  4. Product owner

22- A Sprint planning meeting happens everyday at the same time and place. True or false?

  1. True
  2. False

23- How will The Team know when a backlog item is completed?

  1. The test team say it is completed
  2. The ScrumMaster says it is completed
  3. It meets the team and product owner’s negotiated definition of done
  4. When the Sprint is completed
  5. None of the above

24- In the ‘Manifesto for Agile Software Development’, ‘Working software’ is preferred over which of the following?

  1. Processes and tools
  2. Project managers
  3. Comprehensive documentation
  4. No documentation