QUESTION 1

What kind of software development projects can be executed by Scrum Project Management Framework?
Choice-1: Complete software packages
Choice-2: Customer projects
Choice-3: Sub-systems, components or parts of bigger systems
Choice-4: All kinds of software development projects
Choice-5: None of the given answers

Correct Answer: Choice-4 / All kinds of software development projects


QUESTION 2

What does NOT belong to cornerstones of the agile manifesto?
Choice-1: Individuals and interactions over processes and tools
Choice-2: Working software over comprehensive documentation
Choice-3: Processes over people
Choice-4: Customer collaboration over contract negotiation
Choice-5: Responding to change over following a plan

Correct Answer: Choice-3 / Processes over people


QUESTION 3

What is defined by the Scrum Framework?
A) Rules & Roles
B) Document guidelines
C) Artifacts and events
Choice-1: A
Choice-2: B
Choice-3: C
Choice-4: A, B, C
Choice-5: A, C

Correct Answer: Choice-5 / A, C


QUESTION 4

Where are the customer requirements stored?
Choice-1: In the Product Backlog
Choice-2: In the Sprint Backlog
Choice-3: In a database
Choice-4: In a Scrum Product Requirement Specification
Choice-5: Nowhere. The Scrum Product Owner knows them

Correct Answer: Choice-1 / In the Product Backlog


QUESTION 5

Which ones of the following main roles are defined by Scrum Framework?
A) Scrum Tester
B) The Scrum Team
C) Scrum Manager
D) Scrum Master
E) Scrum Product Owner
Choice-1: A, B, C, D, E
Choice-2: B, C, D, E
Choice-3: B, D, E
Choice-4: A, B, D, E
Choice-5: A, B, C, D

Correct Answer: Choice-3 / B, D, E


QUESTION 6

Which ones of the following main events are defined by Scrum Framework?
A) Sprint Planning Meeting
B) Sprint Retrospective Meeting
C) Sprint Review Meeting
D) Mid-Sprint Status Review Meeting
E) Daily Scrum Meeting
Choice-1: A, B, C, D, E
Choice-2: A, B, C, D
Choice-3: A, C, D, E
Choice-4: A, B, C, E
Choice-5: A, C, E

Correct Answer: Choice-4 / A, B, C, E


QUESTION 7

Which concept is NOT defined in the Scrum Framework?
Choice-1: Scrum Master
Choice-2: Project Manager
Choice-3: Scrum Product Owner
Choice-4: Daily Scrum
Choice-5: Scrum Product Burndown

Correct Answer: Choice-2 / Project Manager


QUESTION 8

What is important in all Scrum projects?
A) Self-organization
B) Clear hierarchies in the company
C) Communication
D) Continuous improvement
Choice-1: A, B, C, D
Choice-2: A, C, D
Choice-3: A, D
Choice-4: A
Choice-5: A, B

Correct Answer: Choice-2 / A, C, D


QUESTION 9

In software engineering what are the disadvantages of the classical waterfall model?
A) End-Product has to be fully anticipated beforehand.
B) Some requirements are implemented as defined in the beginning of the project, and yet they are not really needed by the customer.
C) Each phase is strictly separated.
Choice-1: A
Choice-2: B
Choice-3: C
Choice-4: A, B
Choice-5: A, B, C

Correct Answer: Choice-5 / A, B, C


QUESTION 10

What are the advantages of the Scrum Framework?
Choice-1: Fine-grained requirements are only defined when they are really needed.
Choice-2: All activities to design, build and test a certain functionality are kept together in one phase.
Choice-3: Changes are expected and welcomed by Scrum team.
Choice-4: All of the given answers
Choice-5: None of the given answers

Correct Answer: Choice-4 / All of the given answers